Indobusiness - PT Pertamina Hulu Energi West Madura Offshore, a subsidiary of PT Pertamina, began to operate the field PHE KE-38B. Total production at the beginning of the operation field was 5,400 barrels of oil per day, and 5 million cubic feet of gas per day (mmscfd).
Field development PHE KE-38B, is part of a development plan in 2012. Development of the field has been able to produce 5,400 bpd of oil and 5 mmscfd of gas. Of the total production, 5 mmscfd and 2,100 bpd produced from wells PHE KE-38B1, and 3,300 bpd from the Well PHE KE-38B2. The entire process from initial exploration through production, completed within 8 months and 21 days.
"Drilled exploration well was completed June 22, 2012, and on March 13, 2013 began pumping oil and gas with initial production of 5,400 bpd and 5 mmscfd. Process from initial exploration to production can be done quickly," said Vice President of Corporate Communications PT Pertamina, Ali Mundakir, Sunday (03/17/2013), in Jakarta.
Ali explained that the discussion of PED (exploration discovery to development) has begun intensively since the first wells drilled completed. Thus, all the necessary formalities can be obtained quickly, the process is only two days after the completion of the drilling of a third well.
Drilling can be done by the end of November 2012, and after the POD technically approved, completion of the work done in conjunction with the drilling platform. Platform completed in January 2013.
Completion of the production pipeline between the field and the PHE TO-38B TO-38A was hampered bad weather in January and February. But after the weather improved, the completion of the production pipeline completed on March 11, 2013 and the date of first production wells PHE KE-38B-1 can drained two days later.
"The additional production is expected to contribute, to the government's target to increase national lifting.'s Also for PHE WMO's commitment to reduce their production decline, and as soon as possible to increase production," he said.